The Battle of Stonehenge: what to know about the controversial £1.7bn tunnel project

Building a tunnel on the stretch of the A303 passing Stonehenge has been mooted for years. Now it might become a reality

It’s Britain’s most picturesque traffic jam: a notorious bottleneck on the A303 in Wiltshire, which passes 200 yards from England’s – and possibly the world’s – most famous prehistoric monument, Stonehenge.

For decades, the A303, the most direct route between the Southeast and the Southwest, has been heavily overloaded. Most of this 100-mile corridor between the M3 and the M5 is dual carriageway, but 35 miles (including the Stonehenge section) is single carriageway – which, says Highways England, causes “congestion, delays and an increased risk of accidents”: 24,000 vehicles use the route per day, almost twice as many as it was designed for.

At weekends and in the summer, it’s more like 29,000; it routinely takes an hour or more to pass the short Stonehenge section. So the idea is to build a dual carriageway in a tunnel, thus “removing traffic from much of this iconic setting”, says Highways England.

The full moon sets behind Stonehenge

The full moon sets behind Stonehenge on 27 April, 2021

Finnbarr Webster/Getty Images

When was the plan first hatched?

It was first considered in the 1980s, but progress has been slow and laborious. Plans for a 1.3-mile underground bypass were scrapped in 2007 on cost grounds.

In 2014, the Government’s official roads strategy included £2bn in funding for improvements to the A303 – but was bogged down by funding difficulties.

Then, in November 2020, the Transport Secretary Grant Shapps approved a £1.7bn plan to create a dual carriageway on the eight miles between Amesbury and Berwick Down, including a two-mile tunnel which would run slightly south of the existing A303.

Who objects to this?

The plans have drawn public opposition from local politicians, archaeologists, historians, green campaigners and druids alike. The Stonehenge Alliance, a campaign group, has amassed more than 137,000 objections to the tunnel, arguing that it would do “irreparable damage” to the landscape surrounding Stonehenge – a Unesco World Heritage Site containing a wealth of prehistoric archaeological evidence.

The tunnel itself would pass too deep to cause archaeological damage; it’s the entry points that are the bone of contention. “There would be extensive tunnel cuttings into the chalk for four lanes of tarmac, and massive highway interchanges through sensitive archaeological areas,” says the Stonehenge Alliance. It wants the tunnel to be considerably longer so that the portals don’t endanger the World Heritage Site. Unesco itself supports this position, and has said that the site’s status may be threatened by the plans.

Man protesting the proposed Stonehenge tunnel

A man protests against the building of the Stonehenge tunnel on 21 June, 2020

Finnbarr Webster/Getty Images

What damage could it do?

The Planning Inspectorate had recommended that Grant Shapps should withhold consent, warning it would cause “permanent, irreversible harm”.

A string of sites could be endangered by new cuttings and building work; in total, ten hectares will be churned up. At the western end of the tunnel it could cut through an early Bronze Age settlement. At the eastern end is Blick Mead, an ancient Mesolithic site, where humans gathered thousands of years before Stonehenge was erected.

A treasure trove of finds have been made there: 35,000 pieces of worked flint; the perfectly preserved hoofprints of wild cattle, known as aurochs; as well as a 7,000-year-old dog’s tooth, which has been analysed to show that it began its life far away, probably in northern England. Blick Mead’s integrity could be compromised by the construction of a tunnel entrance a few hundred metres away, and a flyover literally metres from the dig.

Do all experts oppose the plan?

No. Both the National Trust, which owns 800 hectares of land around Stonehenge, and English Heritage, which runs the site itself, are in favour of the tunnel in principle. English Heritage says the scheme “would transform Stonehenge, reunite the landscape and leave a lasting legacy for future generations”.

At present, the World Heritage Site, dotted with monuments, barrows and enclosures, is bisected by the A303: two thirds of its 6,500 acres are on the southern side of the A303, opposite Stonehenge. Grassing over the existing road (which would be turned into a track for walkers and riders) would allow for the restoration of the Stonehenge Avenue, an ancient processional route which currently crosses the A303 en route to the monument from the River Avon.

Is there a third way?

As it stands, the planned scheme is “an unattractive British compromise: a bit of a tunnel, but one that is not long enough to protect the archaeology of the World Heritage Site”, says archaeologist Professor Mike Parker Pearson, a leading expert on Stonehenge.

The Stonehenge Alliance, Unesco and others argue that the tunnel should be made longer to avoid risking damage from the construction of its portals. The Government, though, is adamant that it only has funding for a tunnel of a certain length. English Heritage has warned that a longer tunnel wouldn’t be financially viable, with the result that we would be left with the unsatisfactory status quo.

Stonehenge protest

Arthur Pendragon (centre right with white beard) leads a protest march past the Stonehenge visitor centre on 18 December, 2013

Matt Cardy/Getty Images

Is it actually going ahead?

Currently, that’s unclear. Highways England has said it expects to start building the tunnel between July and September 2022; the construction is expected to take five years to complete.

But a recent ruling by the High Court has thrown a spanner in the works. On 30 July, a judicial review challenging the lawfulness of the Government’s decision sided with the anti-tunnel campaigners. The High Court ruled that Shapps had acted irrationally and unlawfully when he approved the project, and that he did not properly consider alternative schemes - as required by law. It is understood that the project will have to be frozen while the Government considers its next steps.

And even if the project ends up getting the green light, some anti-tunnel campaigners have vowed to take direct action to stop the works from going ahead. “Boris Johnson claimed he’d lie down in front of the bulldozers to stop the third runway at Heathrow,” says Arthur Pendragon, a druid who claims to be an incarnation of the once and future king of England. “I really will lie in front of the bulldozers to stop this.”

 This article was updated on 2 August 2021 to reflect the High Court’s judgement on 30 July

Recommended

Are we heading for a snap general election?
Jacob Rees-Mogg
Today’s big question

Are we heading for a snap general election?

Partygate vs. Cash for Honours: the Boris and Blair rows compared
Tony Blair
In Depth

Partygate vs. Cash for Honours: the Boris and Blair rows compared

Where did the term snowflake come from?
Snowflake
Between the lines

Where did the term snowflake come from?

‘Ambushed by cake’: the many defences of Boris Johnson
Boris Johnson
Why we’re talking about . . .

‘Ambushed by cake’: the many defences of Boris Johnson

Popular articles

What would a Russian ‘lightning war’ against Ukraine look like?
Members of the Kiev territorial defence forces take part in drills outside Kiev, Ukraine
Getting to grips with . . .

What would a Russian ‘lightning war’ against Ukraine look like?

Is Bosnia on the brink of another civil war?
Bosnian Serb leader Milorad Dodik
In Depth

Is Bosnia on the brink of another civil war?

Why is New Zealand shutting its borders again?
Prime Minister Jacinda Ardern adjusts her face mask following a press conference
In Depth

Why is New Zealand shutting its borders again?

The Week Footer Banner